Division Streetscape Update

Project Schedule Changes and Update Date: August 15, 2013 Contact: Joe Annett, Joseph.Annett@portlandoregon.gov To receive emailed project updates, email Joe with “Division” in the subject line. Construction Update Night work that began the week of August 5th...

SE 11th and 12th Avenues reopening

The railroad crossings at SE 11th and 12th Avenues are scheduled to open at 5 a.m. Monday, August 5 as planned. The crossing at SE 8th Avenue is now scheduled to open Wednesday, August 7, when the new traffic signals will be turned on. SE 11th & 12th avenues SE...

Closure of SE 8th, 11th and 12th Avenues

Beginning July 15-August 5, light rail construction where SE 8th, 11th and 12th avenues cross the freight rail tracks and light rail alignment south of Division Street requires closure of these crossings, and detours. To minimize the closure duration crews will...

Water Main Replacement on SE Brooklyn

  The Portland Water Bureau will be installing approximately 280 feet of eight‐inch diameter water main pipe, of which130 feet will be inside a 24‐inch diameter casing pipe on Southeast Brooklyn Street between Southeast Gideon Street and Southeast 16th...